Southern Expansion Substation

Client: Jicarilla Apache Nation

Location: Dulce, NM

Completion: October 2018 – March 2019

Scope/Description:

  • Added a new 115 kV ring bus in the existing 345kV-115kV Station
  • Work included site grading, fencing, concrete, ground grid, pull boxes, conduits, XMFR, breakers, switches, CTs, PTs, CCVTs, LAs, and hard and soft bus