Southern Expansion Substation
Client: Jicarilla Apache Nation
Location: Dulce, NM
Completion: October 2018 – March 2019
Scope/Description:
- Added a new 115 kV ring bus in the existing 345kV-115kV Station
- Work included site grading, fencing, concrete, ground grid, pull boxes, conduits, XMFR, breakers, switches, CTs, PTs, CCVTs, LAs, and hard and soft bus