Broadland Station

Client: Basic Electric Power Cooperative

Location: Huron, SD

Completion: July 2018 – November 2018

Scope/Description:

  • Removed existing concrete piers and re-installed helical anchors
  • 230 kV and 345kV electrical equipment were removed and re-installed after helical anchors were completed
  • Equipment consisted of circuit switchers, CCVTs, MODs, three-phased disconnects, and LAs